Removal of sediment from Al-Fayd Dam in Asir Region
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 16
| Company | Bid amount | Result |
|---|---|---|
| Bawabat Al Fajr Contracting Est. | 8,188,000 SAR | Winner |
| Al Sharhan Energy | 22,770,000 SAR | Bidder |
| CWC | 22,310,000 SAR | Bidder |
| Tuwaiq Al Omraniya Contracting Est. | 20,625,250 SAR | Bidder |
| Saad Mohammed Al Hathal Contracting Est. | 19,359,675 SAR | Bidder |
| Ufuq Global Contracting Est. | 17,422,500 SAR | Bidder |
| Rawabi Arwa Contracting Est. | 14,524,500 SAR | Bidder |
| Salem Hadi Mohammed Al Mubarak Contracting Co. | 13,742,500 SAR | Bidder |
| Al-Haddal Group | 13,397,500 SAR | Bidder |
| Dar Al-Sammar For Contracting Co. | 10,913,500 SAR | Bidder |
| Ramz Al Omran Contracting Co. | 10,878,425 SAR | Bidder |
| Rajaallah Awadh Aidh Al Talhi General Contracting Co. (One-Person Co.) | 9,999,800 SAR | Bidder |
| Fursan Al Dhaiqa General Contracting Co. | 9,947,500 SAR | Bidder |
| Edadat Al-Mustakbl Co. Ltd | 8,084,500 SAR | Bidder |
| Shibl Al Janoub General Contracting Co. | 7,302,500 SAR | Bidder |
| Bin Khammash and Sons | 6,043,250 SAR | Bidder |
Tender Details
- Government agency
- Ministry of Environment, Water and Agriculture
- Tender type
- Public Tender
- Tender number
- 2200021278
- Reference number
- 220839629546
- Branch
- Procurement and Contracts Department
- Region
- Asir Region
- Contract term
- 9 months
- Published
- 2022-08-04
- Bid deadline
- 2022-09-07
- Bid opening date
- 2022-09-08
- Status
- Awarded