Maintenance of median islands and treatment of visual distortions on King Abdullah Road P3
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 6
| Company | Bid amount | Result |
|---|---|---|
| Fal Constructions | 2,260,325 SAR | Winner |
| More Safe Contracting | 2,473,075 SAR | Bidder |
| Nayef Ali Yahya Al Musarra Contracting Est. | 2,239,970 SAR | Bidder |
| SSHCO | 2,156,250 SAR | Bidder |
| Mohammed Sarhan Ali Asiri General Contracting Est. | 2,093,305 SAR | Bidder |
| Sultan Abdullah Al Mansour Contracting Est. | 2,001,288 SAR | Bidder |
Tender Details
- Government agency
- Muhayil Asir Governorate Municipality
- Tender type
- Public Tender
- Tender number
- 2022/287
- Reference number
- 221239844848
- Branch
- Muhayil Municipality
- Region
- Asir Region
- Contract term
- 120 days
- Published
- 2022-12-12
- Bid deadline
- 2023-01-04
- Bid opening date
- 2023-01-05
- Status
- Awarded