Construction of mosques for faculty housing at Qassim University
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 10
| Company | Bid amount | Result |
|---|---|---|
| Al Ajlan Group Ltd | 2,762,683 SAR | Winner |
| Arkan Al Omran Contracting Est. | 5,515,009 SAR | Bidder |
| Bana Al Sharq Projects Co. | 4,706,637 SAR | Bidder |
| Marina Seas | 3,999,602 SAR | Bidder |
| Muhtarif Al Taj Contracting Co. | 3,959,255 SAR | Bidder |
| Kayan Al Bilad Contracting Est. | 3,235,548 SAR | Bidder |
| Abdulmalik Sulaiman Al Saif Contracting Est. | 3,213,077 SAR | Bidder |
| Ehab Mohammed Abdullatif Khalil & Partners Co. (Branch) | 2,690,964 SAR | Bidder |
| Iron Steel Trading Co. | 2,436,256 SAR | Bidder |
| Jiyad Al-Wusta for Contracting | 2,211,789 SAR | Bidder |
Tender Details
- Government agency
- Qassim University
- Tender type
- Public Tender
- Tender number
- 2023/40
- Reference number
- 230539964830
- Branch
- Contracts and Tenders Department
- Region
- Qassim Region
- Contract term
- 540 days
- Published
- 2023-06-01
- Bid deadline
- 2023-07-18
- Bid opening date
- 2023-07-18
- Status
- Awarded