Maintenance of toilets by removing and replacing cladding
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 10
| Company | Bid amount | Result |
|---|---|---|
| Masar Sinnar Contracting Est. | 285,660 SAR | Winner |
| Aram | 698,625 SAR | Bidder |
| Durar Al Faihaa Contracting Est. | 605,475 SAR | Bidder |
| Emaar Al Maaden Contracting Est. | 574,425 SAR | Bidder |
| Rukn Al Zawaya Aluminium Factory | 543,375 SAR | Bidder |
| Adawat Al Binaa Building Materials Est. | 419,175 SAR | Bidder |
| Al Mishari Al Ghali Contracting Est. | 395,888 SAR | Bidder |
| Ruaya Aldar | 341,550 SAR | Bidder |
| Delta Facility Management Operation & Maintenance Co. (One-Person Co.) | 328,043 SAR | Bidder |
| Basma Wa Ruya Advertising Agency | 298,080 SAR | Bidder |
Tender Details
- Government agency
- Al-Wajh Governorate Municipality
- Tender type
- Public Tender
- Tender number
- 35
- Reference number
- 230739008956
- Branch
- Al-Wajh Governorate Municipality
- Region
- Tabuk Region
- Contract term
- 30 months
- Published
- 2023-07-15
- Bid deadline
- 2023-08-01
- Bid opening date
- 2023-08-01
- Status
- Awarded