Development and rehabilitation of Wadi Al-Difa walkway in Madinah
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 6
| Company | Bid amount | Result |
|---|---|---|
| Ethmar | 16,759,135 SAR | Winner |
| Zaid Group | 53,411,229 SAR | Bidder |
| Al Abraqain Arabian Contracting Co. | 31,579,811 SAR | Bidder |
| RTC | 19,741,830 SAR | Bidder |
| Rawabi Al Hamra Contracting Co. | 19,702,427 SAR | Bidder |
| Arabian Projects Contracting Co. Ltd. | 17,929,317 SAR | Bidder |
Tender Details
- Government agency
- Madinah Region Municipality
- Tender type
- Public Tender
- Tender number
- 87044465
- Reference number
- 230739017722
- Branch
- Procurement and Contracts
- Region
- Madinah Region
- Contract term
- 24 months
- Published
- 2023-07-27
- Bid deadline
- 2023-08-26
- Bid opening date
- 2023-08-27
- Status
- Awarded