Supply, installation, operation and testing of a 25-ton central air conditioner at the operations center site
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 4
| Company | Bid amount | Result |
|---|---|---|
| Cooling Funoon | 97,750 SAR | Winner |
| Al Taqniya Al Ihtirafiya Operation & Maintenance Co. (One-Person Co.) | 150,321 SAR | Bidder |
| Al Taj Trading & Contracting Co. Ltd. | 135,000 SAR | Bidder |
| Al Khubaraa Al Muhtarifoon Air Conditioning Works Est. | 98,900 SAR | Bidder |
Tender Details
- Government agency
- Royal Saudi Air Defense Forces
- Tender type
- Direct Purchase
- Tender number
- 2023/60
- Reference number
- 230839005457
- Branch
- (Jeddah Section) - Engineering and Works Department
- Region
- Makkah Region
- Contract term
- 75 days
- Published
- 2023-08-08
- Bid deadline
- 2023-08-18
- Status
- Awarded