Execution of floor renovation works for the main and secondary corridors at General Staff Headquarters building no. (1)
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 14
| Company | Bid amount | Result |
|---|---|---|
| Imtilak Al Jazeera Contracting Co. | 2,828,189 SAR | Winner |
| Al Anthima Al Ilmiya Contracting Co. (One-Person Co.) | 9,600,805 SAR | Bidder |
| Safelco | 6,742,487 SAR | Bidder |
| Teef Najd | 5,819,583 SAR | Bidder |
| شركة صحارى لخدمات الصيانة المحدوده | 5,743,894 SAR | Bidder |
| Khuta Al Tamayuz Contracting Co. (One-Person Co.) | 5,194,602 SAR | Bidder |
| Tal Al Amara | 4,752,521 SAR | Bidder |
| Wasl Al Afaq Maintenance and Contracting Co. | 4,132,078 SAR | Bidder |
| Motamakena | 3,720,272 SAR | Bidder |
| Abdulwahab Jammah Al Ghamdi Trading Co. | 3,347,124 SAR | Bidder |
| Azal International Company | 3,344,166 SAR | Bidder |
| Zimam Company | 3,226,994 SAR | Bidder |
| Al-HATHAL Contracting | 2,988,338 SAR | Bidder |
| Amtar Al Arid General Contracting Co. (One-Person Co.) | 2,898,476 SAR | Bidder |
Tender Details
- Government agency
- Presidency of the General Staff
- Tender type
- Public Tender
- Tender number
- 1 / 1 / 833
- Reference number
- 231039009581
- Branch
- Military Works
- Region
- Riyadh Region
- Contract term
- 360 days
- Published
- 2023-11-13
- Bid deadline
- 2023-12-05
- Bid opening date
- 2023-12-06
- Status
- Awarded