Supply of distribution board control units
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 4
| Company | Bid amount | Result |
|---|---|---|
| Rukn Al Sultan First General Architectural Contracting Est. | 4,880,313 SAR | Winner |
| Baddah Mishaan Baddah Al Sahli Contracting Est. | 5,485,270 SAR | Compliant |
| شركة كرم الوطن المحدودة | 4,970,875 SAR | Compliant |
| شركة دلتا السعوديه المحدودة | 3,622,500 SAR | Non-compliant |
Tender Details
- Government agency
- Hafr Al-Batin Municipality
- Tender type
- Public Tender
- Tender number
- 2024/97
- Reference number
- 240639008450
- Branch
- Hafr Al-Batin Municipality
- Region
- Eastern Province
- Contract term
- 2 months
- Published
- 2024-06-11
- Bid deadline
- 2024-06-27
- Bid opening date
- 2024-06-27
- Status
- Awarded