Rehabilitation of electrical infrastructure at King Faisal Military City and its affiliated units (phase 1)
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 11
| Company | Bid amount | Result |
|---|---|---|
| Al Shabakat Al Kubra Contracting Est. | 3,690,350 SAR | Winner |
| Sara International Trading & Contracting Co. (One-Person Co.) | 26,996,940 SAR | Compliant |
| Binjarallah Co | 14,421,000 SAR | Compliant |
| Australian Building Technology Co. Ltd. | 10,663,619 SAR | Compliant |
| Ruwad Arabian General Contracting Est. | 10,465,000 SAR | Compliant |
| Haif Trading & Contracting Co. | 6,819,348 SAR | Compliant |
| Al Awtan Modern General Contracting Co. (One-Person Co.) | 4,432,100 SAR | Compliant |
| Alkobraish Group | 4,226,250 SAR | Compliant |
| Saeed Abdullah Bin Atat Al Qahtani Contracting Co. | 3,942,200 SAR | Compliant |
| Al Wasat Al Ganouby | 3,923,050 SAR | Compliant |
| Al Rajhi Electric Co. | 4,637,844 SAR | Non-compliant |
Tender Details
- Government agency
- Royal Saudi Land Forces
- Tender type
- Public Tender
- Tender number
- م/45/171
- Reference number
- 240739016823
- Branch
- King Faisal Military City Administration, Khamis Mushait
- Region
- Asir Region
- Contract term
- 90 days
- Published
- 2024-07-25
- Bid deadline
- 2024-08-27
- Bid opening date
- 2024-08-27
- Status
- Awarded