Asphalting of grant plots in Makkah (Jabal Al-Sayyida Khadija plan, amended 2 – Khumaym Kudai District plan – Rawabi Kudai plan – Al-Akaishiyah plan)
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 14
| Company | Bid amount | Result |
|---|---|---|
| MAMPCO | 16,406,130 SAR | Winner |
| Al-JAZERA | 26,466,227 SAR | Compliant |
| Sunnaa Al Qimma General Contracting Co. | 20,923,100 SAR | Compliant |
| Asasiyat Al Turuq Contracting Est. | 17,892,850 SAR | Compliant |
| Awtad Asia General Contracting Est. | 17,710,000 SAR | Compliant |
| Almatrafy | 14,740,700 SAR | Compliant |
| AL-Madaifi Contracting Company Ltd | 14,265,980 SAR | Compliant |
| Maher Al Qurashi | 13,803,200 SAR | Compliant |
| RACO | 15,812,500 SAR | Non-compliant |
| Fahad Talq Mutlaq Al Suwaihiri & Partners Co. Ltd. | 14,993,470 SAR | Non-compliant |
| Manahi Bijad Manahi Al Gharmoul Al Buqami General Contracting Co. (One-Person Co.) | 14,330,150 SAR | Non-compliant |
| Arkan Roads & Electricity Co. (One-Person Co.) | 12,993,620 SAR | Non-compliant |
| Itlalat Al Mustaqbal General Contracting Co. | 12,836,760 SAR | Non-compliant |
| Mamal Al Binaa Contracting Co. Ltd. | 7,291,161 SAR | Non-compliant |
Tender Details
- Government agency
- Holy Makkah Municipality
- Tender type
- Public Tender
- Tender number
- 24/160
- Reference number
- 241039002663
- Branch
- Procurement Department
- Region
- Makkah Region
- Contract term
- 36 months
- Published
- 2024-10-03
- Bid deadline
- 2024-11-04
- Bid opening date
- 2024-11-04
- Status
- Awarded