Maintenance, asphalting and lighting works for the governorate and its affiliated centers and villages
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 14
| Company | Bid amount | Result |
|---|---|---|
| Banan Al Tamayuz Contracting Est. | 1,607,240 SAR | Winner |
| Tatweer Arabian Contracting Est. | 3,373,640 SAR | Compliant |
| Al Sudaif Operation & Maintenance Co. (One-Person Co.) | 2,912,950 SAR | Compliant |
| Sas Kotr General Contracting Co. | 2,620,045 SAR | Compliant |
| Waheed Mohammed Ali Taweel General Contracting Est. | 2,497,570 SAR | Compliant |
| Khalid Mohammed Hassan Asiri Contracting Est. | 2,352,153 SAR | Compliant |
| Binaa Al Sahil | 2,247,618 SAR | Compliant |
| Sadf United Contracting Co. | 1,998,240 SAR | Compliant |
| Sultan Saeed Mubarak Al Qahtani General Contracting Est. | 1,962,648 SAR | Compliant |
| Forsan Alorouba | 1,948,445 SAR | Compliant |
| Abdulrahman Ali Mohammed Al Hilali Contracting Est. | 1,896,178 SAR | Compliant |
| Tatweer Al Waqi General Contracting Est. | 1,887,840 SAR | Compliant |
| Al Mudun Al Mustaqbaliya General Architectural Contracting Co. | 1,781,753 SAR | Compliant |
| Al Ufuq Abr Al Khaleej General Contracting Est. | 2,385,790 SAR | Non-compliant |
Tender Details
- Government agency
- Al-Birk Municipality
- Tender type
- Public Tender
- Tender number
- 2025/004
- Reference number
- 250239011701
- Branch
- Al-Birk
- Region
- Asir Region
- Contract term
- 90 days
- Published
- 2025-02-18
- Bid deadline
- 2025-03-06
- Bid opening date
- 2025-03-06
- Status
- Awarded