Asphalting of the villages of Balqarn Governorate
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 10
| Company | Bid amount | Result |
|---|---|---|
| Arkan Aljazeera General Contracting | 786,784 SAR | Winner |
| Mohammed Saad Ali Al Qarni Contracting Est. | 1,254,420 SAR | Compliant |
| Manarat Al Shamal Contracting Co. | 1,137,764 SAR | Compliant |
| Forsan Alorouba | 1,101,700 SAR | Compliant |
| Nahr Al Tashyeed Contracting Est. | 1,019,268 SAR | Compliant |
| ARTZ | 991,990 SAR | Compliant |
| Honest Contracting Est. | 974,280 SAR | Compliant |
| Sakhrat Baihan Contracting Est. | 947,485 SAR | Compliant |
| Al Sudaif Operation & Maintenance Co. (One-Person Co.) | 848,677 SAR | Compliant |
| Mohammed Abdullah Hassan Al Shehri General Contracting Est. | 789,544 SAR | Compliant |
Tender Details
- Government agency
- Balqarn Governorate Municipality
- Tender type
- Public Tender
- Reference number
- 250339007858
- Branch
- Balqarn Municipality
- Region
- Asir Region
- Contract term
- 180 days
- Published
- 2025-03-12
- Bid deadline
- 2025-03-28
- Bid opening date
- 2025-03-28
- Status
- Awarded