Fitting out the headquarters of the Renewable Energy and Environmental Technology Center at the College of Medicine, building 25
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 5
| Company | Bid amount | Result |
|---|---|---|
| NABNY | 288,261 SAR | Winner |
| Al Wajd Arabian Co. | 392,495 SAR | Compliant |
| Ostool Al Nahda Est. | 345,000 SAR | Compliant |
| Saud Bin Sarhan Al Hathli General Contracting Co. | 144,900 SAR | Compliant |
| Nawaf Saad Al Anazi Contracting Est. | 293,977 SAR | Non-compliant |
Tender Details
- Government agency
- University of Tabuk
- Tender type
- Public Tender
- Reference number
- 251039005183
- Branch
- Contracts and Procurement Department
- Region
- Tabuk Region
- Contract term
- 2 months
- Published
- 2025-10-12
- Bid deadline
- 2025-10-28
- Bid opening date
- 2025-10-28
- Status
- Awarded