Works for removing the existing wall and constructing a new wall for faculty members' villas
The project period depends on the site handover or start approval date, so this is an estimate that varies by agency and project
Submitted Bids 6
| Company | Bid amount | Result |
|---|---|---|
| Al Manara Al Umraniya General Architectural Contracting Co. | 89,800 SAR | Winner |
| Emaar Al Khaleej Projects Co. | 174,000 SAR | Compliant |
| Al Musheed Golden General Contracting Est. | 139,150 SAR | Compliant |
| Al Arab United Co. | 124,000 SAR | Compliant |
| Al Falih Contracting Est. | 100,165 SAR | Compliant |
| Aali Al Jawda Contracting Est. | 99,728 SAR | Non-compliant |
Tender Details
- Government agency
- University of Hail
- Tender type
- Public Tender
- Tender number
- 26/0076
- Reference number
- 260639004242
- Branch
- University of Hail
- Region
- Hail Region
- Contract term
- 30 days
- Published
- 2026-06-15
- Bid deadline
- 2026-07-01
- Bid opening date
- 2026-07-01
- Status
- Awarded